Day 184: Today, Oct 29th, is exactly 6 months since we signed the contract
for the home improvement project with RPM Builders. We've come a long way!
Steve did a lot of work on the stair railings. The hand rails still need
to be installed, but the railing around the opening is in and looks great!
Rich painted the bathroom and got the vanity installed. It still needs a
countertop, but that has already been ordered.
Kevin installed a bunch of base board. Rich and Phil did lots of painting.
We'll be moving our bedroom into the finished rooms by the end of the week.
That will allow them to floor and paint out bedroom, which is the last room
on the main floor.
|